24 November 2026
Project No. K6749

Diamond Head seawall and parkland improvements

Hello Golden Beach community, 

Thanks for staying connected and signing up for updates about projects happening in your neighbourhood. 

Exciting progress is about to begin at Diamond Head, with works on the first stage of the Diamond Head seawall and foreshore improvements project expected to start in late December.

In short

  • Late December 2026: Site establishment, temporary fencing, site sheds and the northern section of the car park will close. 
  • 4 January 2027: Major construction works begin. 
  • Temporary pedestrian detours, work zones and some parking changes will be in place during construction.
  • Local cafés and businesses remain open and ready to welcome you.

A stronger future for Diamond Head

This important project will help protect the Golden Beach foreshore from coastal erosion and storm impacts while improving resilience to future coastal hazards and climate change. 

The first stage of works will focus on the area between Lamerough Canal and the June Street boat ramp and includes a new seawall, drainage upgrades, a new beach access ramp and improvements to the foreshore. 

Designed in response to the impacts of the Bribie Island breakthrough and recent severe weather events, these works are an important investment in the future of our coastline. 
Location of works, Diamond Head

What's being built?

The first stage of construction will focus on the section between Lamerough Canal and the June Street boat ramp.

The project includes:
  • a new adaptable seawall to help protect the foreshore
  • drainage upgrades to improve stormwater management and lessen nuisance flooding
  • part of the seawall will be rock and coloured concrete crest walls
  • part of the seawall between the groyne and jetty will be a sandstone-coloured terraced seawall with access stairs and handrails
  • a new 2-metre-wide beach access ramp to make it easier for people of all abilities to get to the shoreline
  • landscaping, carparking and overall foreshore improvements to improve resilience to coastal hazards and climate change.
Construction is expected to be completed by September 2027, subject to weather and site conditions.

Timing of works

Construction will be delivered in stages, subject to weather and site conditions. 
Key dates include: 
  • Late December 2026: Site establishment, including temporary fencing and site sheds. The northern section of the car park will close during this time. 
  • 4 January 2027: Major construction works begin. 
  • January to late July 2027: Seawall construction will progress from north to south across the project area. 
  • Late July to September 2027: Civil works, landscaping and site restoration will be completed. 
  • September 2027: Construction is expected to be complete. 
We'll continue to keep our community informed as works progress. 
Visit the project webpage for more information >

What to expect during construction

Parking and pedestrian access 
We understand construction can be disruptive and will work to minimise impacts where possible. 
  • Temporary work zones and safety fencing will be in place throughout construction to keep everyone safe. 
  • A signed pedestrian detour will be implemented from January to September 2027, with access routes clearly marked on site. 
  • Some temporary parking restrictions and changes will also be required, including the closure of the northern section of the car park during site establishment and construction. 
  • Access will remain available to nearby beaches south of the construction zone and sections of the coastal pathway outside the work area. 
Boat ramp access 
  • To allow construction to be safely completed, access to the boat ramps will be temporarily closed from April to late July 2027. 
  • Final closure dates will be confirmed and communicated closer to the time. 
We appreciate our community's patience and understanding while these important works are completed. 

Construction activity 
  • Residents and visitors may notice increased construction traffic, machinery movements and some noise while works are underway. 
  • Construction will be carefully staged to respond to local coastal conditions and consider future changes within the Pumicestone Passage. 
Thank you for your patience as we deliver these important improvements for the Golden Beach community. 

Local cafés, restaurants and businesses remaining open throughout the project. 

Keith Hill Park improvements

Community feedback played an important role in shaping the final design for Keith Hill Park. The final design has now been completed and reflects community feedback alongside technical, environmental, safety and budget considerations.

Proposed upgrades include improved pathways, seating, shelters and picnic facilities that will help the park remain safe, accessible and enjoyable into the future.

You can read more about the community engagement on the Have your Say Sunshine Coast project page.   

Stay connected

We’ll share updates online on the project webpage and via email to people who register to receive them.

Please share this with people who may have an interest in the project including staff, suppliers, clients and customers, property managers/landlords, family and friends, and encourage them to subscribe. 
  • Online: visit the project website 
  • Subscribe: to receive email updates on the Golden Beach foreshore works (including the Diamond Head seawall construction)
  • Email: CoastalLakesandWetlands@sunshinecoast.qld.gov.au
The Diamond Head seawall project is supported by the Queensland government's QCoast2100 program Round 4, which is delivered in partnership with the LGAQ and is jointly funded by the Australian and Queensland governments under the Disaster Recovery Funding Arrangements.
Subscribe to receive updates on the Golden Beach foreshore works >




            
 

Unsubscribe // Discover other Newsletters // Privacy Policy

Sunshine Coast Council sent this message to , these details are included to help provide assurance that this is a genuine email from Sunshine Coast Council. Any personal details and data acquired by the Council from participation in any online services will be used only for the purpose it was collected and in accordance with Council’s Privacy Policy.

 

Sunshine Coast Council acknowledges the Sunshine Coast Country, home of the Kabi Kabi peoples and the Jinibara peoples, the Traditional Custodians, whose lands and waters we all now share.

We commit to working in partnership with the Traditional Custodians and the broader First Nations (Aboriginal and Torres Strait Islander) community to support self-determination through economic and community development.

 

Copyright © Sunshine Coast Council, all rights reserved.